WELCOME TO YOUR UPDA/MMUP MOCK EXAM
FUTURE POINT Providing around 30 updated Module Live mock test Customized from Previous Year UPDA Exam Questions also additionally we are providing our own new questions pattern for engineers can easily understanding and achieve UPDA license in first attempt .Our trainers are well experienced who guide engineers in a right direction here engineers can attend class room training and clarify the doubts face to face .You should attend the class regularly and practice the topic which studied, also go through the questions which providing by trainer or Institute. Attending class face to face is more effective than online and recorded sessions so you can have a refreshment in your memory what you studied years back. practice mock sessions equal to your exam and evaluate yourself, your marks and performance.
1.
Consider the following Statements:
Entertainment of air in concrete is done so as to
- Increase the Workability
- Increase the Strength
- Increase the resistance to freezing and Thawing
Which of the above statement is/are correct?
2.
The maximum vertical shearing stress due to VQ/lb in teh beam with a rectangular cross section
3.
the I thermocapillary nature of engineering has implication for appropriateness for specialization. Which of the following is correct?
4.
The flow immediately upstream of a hydraulic Jump is:
5.
The forward pass in project network calculations determines the
6.
The following relation means: A → B -2
7.
The intersection of the WBS and the OBS is the:
8.
What is the yield strength for most reinforcing bars:
9.
Which of the following situations required a change order:
10.
In order to provide the geometric standard for each roadway/highway component, what is that needs to be established first?
12.
Structures are most sensitive to:
13.
The slump test is used for:
14.
22A bid manager is in charge of a closed bid in which several firms are involved. The last day of the bidding period arrives and one firm has not yet submitted an entry. Bbob calls the firm and asks if they are going to submit a bid and they say they have been too busy to write a proposal but might be able to get one worked out by the next day. He should
15.
Consider the following statements
In a simply supported beam subjected to uniformly distributed load throughout the length, at which points is the stress due to (i) flexure and (ii) shear equal to zero selectively is the stress
- At support section at neutral fiber
- At mid span section at neutral fiber
- At mid span section a top fiber
- At support section at bottom fiber
Which of the above stream is correct?
16.
Increased water-cement ratio(W/C) in concrete mix
17.
The ratio of the maximum normal stress due to maximum vertical shearing stress in a cantilever beam of length (L), with and loaded at the end is given by
18.
Consider the following characteristics regarding timber.
- Stronger Variety
- Ability to take very smooth finish
- Toughness
- Difficult to season
Which of the above characteristics is/are essential for timber to be used as beams?
19.
Structural fill is required to support a slab-on-grade in a n area with a deep frost line. To avoid potential problem with frost heave, the best material for structural fill would be
20.
What loads are considered as construction loads?
21.
Inspections are also called
22.
Consider steady and uniform flow in a prismatic channel. The channel is trapezoidal in cross section, with a base of width 5ft and sides. the channel slopes 10 feet over its 0.5-mile length. Where is the velocity the greatest in the channel?
23.
Road project needs a gravel base. Which gravel do you recommend for the project?
24.
The factors that govern the workability of fresh concrete are?
25.
A bid for foundation construction is based on owner supplied soil boring test results showing sandy clay to a depth of 6m. However, during construction, the backhoe encounters Large pieces of concrete buried throughout the construction site. This situation would normally be referred to a s?